Free Standard AU & NZ Shipping For All Book Orders Over $80!
Register      Login
The APPEA Journal The APPEA Journal Society
Journal of Australian Energy Producers
RESEARCH ARTICLE (Non peer reviewed)

Rigless well intervention and trees on wire from a DPII vessel: a case study

Simon Glennie A , Tom Leeson B , Ian Rowson B and Bevan Morrison B

Bevan Morrison presented this extended abstract to the 49th APPEA Conference on Monday, 1 June 2009 in Darwin.

+ Author Affiliations
- Author Affiliations

A Woodside Energy Ltd 240 St Georges Terrace Perth, WA 6000

B TSMarine Pty Ltd

The APPEA Journal 49(2) 564-564 https://doi.org/10.1071/AJ08037
Published: 2009

Abstract

The Vincent field development is typical subsea development with 11 subsea wells required to be tied back to a central production facility.

In 350–400 m of water all subsea operations would be diver-less and the well costs associated with using a semi-submersible rig would be a major element of the total field cost.

Sequencing construction vessel and drill rig activities, and aligning this sequence with availability of suitable vessels is often a major challenge on such projects. This was accentuated on this development by the shortage of suitable vessels. In addition to this, multiple mobilisations—potentially incorporating lengthy, expensive transits from Singapore—drove a desire to minimise the use of specialist vessels.

The challenges in reducing well costs by using rigless operations are both technical and commercial. Technically, the operations and proposed equipment must be matched to the capabilities and functionality of the vessel. Commercially, sufficient work needs to be identified to justify the one-off costs of preparing and mobilising the vessel and equipment, preparing the operations program, and training and familiarising the personnel.

In this instance, the operator identified sufficient work to make the vessel mobilisation and equipment preparation worthwhile while not committing to a long-term deployment. Recognising the multi-role capability of the vessel permitted additional work on nearby assets. These removed the need to mobilise additional vessels to the field and improved vessel’s economy in well intervention mode.

Other factors that ensured value was gained from the rigless approach included:

  1. the rig schedule being de-coupled from product delivery;

  2. the drilling program with limited drilling assets was accelerated, protecting first oil; and,

  3. the need to re-configure or modify a rig for Xmas tree (XT) handling was removed.

Initial preparations for the planned operations began in the latter part of 2006. The main activities were to:

  1. confirm the specification of the subsea lubricator system and its deployment system;

  2. undertake a detailed hazard and risk assessment process on all operations;

  3. undertake an operability study for crane and deployment system;

  4. complete the modifications to the vessel for its intervention role; and,

  5. prepare detailed well programs and procedures for equipment operation.

The design and fabrication of project-specific interface equipment between the subsea lubricator and the subsea Xmas trees, and specification of the required well services equipment such as wireline, pumping and fluid handling services were also required.

As this represented the first time such operations had been undertaken in the region by the contractor or by the operator, a large number of supporting systems were required to be developed, adopted and managed, most notably:

  1. well control and barrier philosophies;

  2. emergency shutdown and disconnection (ESD) philosophy;

  3. project management processes; and,

  4. personnel training and familiarisation programs.

keywords: Rigless well intervention, Xmas trees, SSXT, Vincent Field, North West Shelf, monohull vessel, trees on wire, DP vessel, LWI, light well intervention, subsea cost saving

After completing a BSc in chemical engineering and a PhD in biochemical engineering at The University of Birmingham in the UK, Tom entered the oil industry as a well operations supervisor with Shell. After periods in Oman, the Brent field in the UK, and the Netherlands, Tom crossed over to join the service sector. A variety of roles in production operations, and well testing, intervention and abandonment operations followed within The Expro Group and subsequently Acteon. In 2006, he joined TSMarine as commercial manager. Now, with 20 years in the industry, Tom is the sales and technology manager responsible for developing and marketing the company’s well intervention capability.

Simon.glennie@woodside.com.au

Ian has worked in the offshore oil and gas industry for over 18 years with the majority of this time working with offshore installation contractors. His varied experience has included offshore roles as project engineer and ROV pilot to onshore design draftsman, tendering and commercial through to sales and marketing and general management. Ian was responsible for initially opening the Perth office of TSMarine mid 2006.

Ian.Rowson@tsmarine.net.au

Bevan left Auckland University in New Zealand with a Bachelor of Technology in optoelectronics (Hons) and spent the next 11 years with Schlumberger Oilfield Services, initially working in Indonesia and offshore Thailand specializing in wireline logging and intervention services. He then cross trained to the drilling and measurements segment of Schlumberger and spent a year modelling and geo-steering horizontal wells in Egypt and China before moving into line management in Egypt. Following this he moved into sales, marketing and business development, initially in Egypt but then these skills took him to The Sudan as sales manager before moving to Australia as east coast sales manager for Wireline services. In 2008 he joined TSMarine to lead the business development of the fast-growing well intervention market in Asia-Pacific. He is presently based in Perth, Australia but travels frequently across Australasia.

Bevan.Morrison@tsmarine.net.au