THE DEVELOPMENT OF THE TIRRAWARRA OIL AND GAS FIELD

H. T. Pecanek and I. M. Paton

The APPEA Journal 24(1) 278 - 288
Published: 1984

Abstract

The Tirrawarra Oil and Gas Field, discovered in 1970 in the South Australian portion of the Cooper Basin, is the largest onshore Permian oil field in Australia. Development began in 1981 as part of the $1400 million Cooper Basin Liquids Project

The field is contained within a broad anticline bisected by a north-south sealing normal fault. This fault divides the Tirrawarra oil reservoir into the Western and Main oil fields. Thirty-four wells have been drilled, intersecting ten Patchawarra Formation sandstone gas reservoirs and the Tirrawarra Sandstone oil reservoir. Development drilling discovered three further sandstone gas reservoirs in the Toolachee Formation.

The development plan was based on a seven-spot pattern to allow for enhanced oil recovery by miscible gas drive. The target rates were 5400 barrels of oil (860 kilolitres) per day with 13 million ft3 (0.37 million m3) per day of associated gas and 70 million ft3 (2 million m') per day of wet, non-associated gas. Evaluation of early production tests showed rapid decline. The 100 ft (30 m) thick, low-permeability Tirrawarra oil reservoir was interpreted as an ideal reservoir for fracture treatment and as a result all oil wells have been successfully stimulated, with significant improvement in well production rates.

The oil is highly volatile but miscibility with carbon dioxide has been proven possible by laboratory tests, even though the reservoir temperature is 285°F (140°C). Pilot gas injection will assess the feasibility of a larger-scale field-wide pressure maintenance scheme using miscible gas. Riot gas injection wells will use Tirrawarra Field Patchawarra Formation separator gas to defer higher infrastructure costs associated with the alternative option of piping carbon dioxide from Moomba, the nearest source.